PURCHASER:
HRVATSKA ELEKTROPRIVREDA

TYPE OF DOCUMENTATION:
Preliminary studies, Conceptual Design, Final Design, Detailed Design, As-built Design

DESCRIPTION:
One of the major projects that Elektroprojekt worked on was EL-TO Zagreb Combined Heat and Power (CHP) Combined-Cycle Cogeneration Plant, i.e. 150 MWe/114 MWt Unit L
(replacement of Unit A with a new combined-cycle cogeneration power plant).
 
Within the design preparation activities, Elektroprojekt provided the services of the project engineer, carried out Conceptual Design amendments, the planning permission amendments, and prepared the Environmental Protection Study. The Final Designs (phases 1 and 2), Detailed Designs (phases 1 and 2) and tender documentation for equipment contracting, including procurement specifications and technical specifications, were created.
 
Within the project construction activities, Elektroprojekt also provided consulting services to the EPC contractor (the Fata EPC company).
 
After the completion of the construction, the As-built Design documentation will be prepared and the operating permit obtained. 


elektroprojekt d.d.
Alexandera von Humboldta 4
10000 Zagreb
tel: +385 (01) 6307 777
CONTACT US